Logbook, first day on run
PLANNING and events (Luca Gennaro Foggetta)
Each day, meeting at 1100
DAFNE Environment(Paolo Ciuffetti,Francesco Galletti,Alessandro Stecchi)
BTF Magnet offline, removed from DBFiles, so BTF One electron will not work!!!!
BTF environment (Luca Gennaro Foggetta,Claudio Di Giulio)
We start to fill doc for setup a correct testbeam on How to setup a TESTBEAM
BTF up in the morning with all checks performed
Copy of the BTF DAQ for !CHAOS in operation
!CHAOS environment(Claudio Bisegni)
!CHAOS ready since one month, check connection ok
!CHAOS infrastructure (Riccardo Gargana)
Up and ready, also for assistance and backup
WEB UI (Paolo Ciuffetti, Unknown User (gioscio))
We start to use the old WEBUI for the first days, the new WEBUI js is under debug .
WEBCAM (Stefano Pioli,Giampiero Di Pirro)
Gargana setup a new VM on BTF rack server, vwbtfhacam001 at 192.168.189.132, internal network 10.10.10.5. The BTF basler SCA1300-32GM is on the internal network address 10.10.10.3
SCRAPERS (Francesco Galletti,Salvatore Caschera)
The test setup is on, and we reach
MAGNETS CU and DRIVER (Andrea Michelotti,Alessandro D'Uffizi)
DEBUG
DAQ CU and DRIVER (Andrea Michelotti,Luca Gennaro Foggetta)
DEBUG, problem with the repaired V513 module, some noise pickup on the V792 gate.
DISCUSSIONS
SAVE RESTORE discussion on SAVE RESTORE features